What is the difference between project scope and project requirements.

a. Project scope defines the boundaries of the project while project requirements define what is needed to achieve the project goals
b. Project scope defines what is needed to achieve the project goals while project requirements define the boundaries of the project
c. Project scope is a high-level statement of project goals while project requirements are a detailed description of project deliverables
d. Project scope is a detailed description of project deliverables while project requirements are a high-level statement of project goals
Answer: a. Project scope defines the boundaries of the project while project requirements define what is needed