A activity in a network diagram is said to be……….if the delay in its start will further delay the project completion time. / Computer Based Optimisation Techniques MCQs, Computer Science and I.T Subjects / By The Professor A. forward pass B. backward pass C. critical. D. non-critical. ANSWER: C