In PERT for an activity, the optimistic time 2, the pessimistic time is 12 and most-likely time is 4. What is the expected time. / Computer Science and I.T Subjects, Data Communication and Networks / By The Professor A. 0 B. 1 C. 5 D. 6 ANSWER: C